Domain 1: Massachusetts Administrative Responsibilities (780 CMR)

Question 1

A retaining wall is 9 feet 6 inches high from the bottom of its footing to the top of the wall, and the top is 5 feet 2 inches above finished grade. The work otherwise requires a building permit. What is the correct licensing and supervision determination?

Show answer & explanation

Correct answer: A - It is within the Unrestricted CSL scope, and the wall is a required on-site supervision checkpoint

Domain 2: Plan Reading and Estimating

Question 2

A renovation estimate includes $28,000 for labor, $32,000 for materials, $20,000 for subcontractors, and $4,000 for project overhead. Add a 5% contingency to the estimated cost, then set the price for a 20% gross margin, defined as gross profit divided by selling price. What bid is required?

Show answer & explanation

Correct answer: D - $110,250

Domain 3: General Building Construction Knowledge

Question 3

A second-floor sleeping room has an emergency escape window with a 30-inch clear width, 27-inch clear height, and sill 42 inches above the floor. Net clear opening is measured through the fully open sash. How should the window be classified?

Show answer & explanation

Correct answer: A - Noncompliant: the 5.625-square-foot opening is below the 5.7-square-foot minimum

Domain 4: Energy Efficiency

Question 4

A new Massachusetts dwelling is designed as all-electric and uses the HERS compliance path. Its final HERS Index is 44. A reviewer rejects it by applying the mixed-fuel new-construction maximum of 42. How should the reviewer apply the HERS limit?

Show answer & explanation

Correct answer: B - Use the all-electric maximum of 45; HERS 44 complies because lower scores are better

Domain 6: Sitework and Foundations

Question 5

After heavy rain, water appears along a basement wall-floor joint. Downspouts discharge beside the foundation, exterior grade falls toward the house, and the below-grade walls have dampproofing but no exterior waterproofing. No cracking or wall movement is visible. Which corrective sequence addresses the most likely mechanism?

Show answer & explanation

Correct answer: B - Correct runoff and grading first; if hydrostatic pressure persists, add exterior waterproofing and footing drainage

Domain 7: Concrete and Masonry

Question 6

An anchored brick veneer has a 1.5-inch clear airspace. Ties are spaced 24 inches horizontally and 12 inches vertically. Additional ties are 8 inches from opening edges at 30 inches on center. Flashing is continuous, but weeps are 40 inches on center. Which correction is necessary?

Show answer & explanation

Correct answer: D - Reduce weep spacing to 33 inches on center or less

Domain 9: Structural Framing (Steel and Wood)

Question 7

During rough framing, a plumber cuts a 3-inch-long notch through the bottom flange of an engineered wood I-joist. The manufacturer's hole chart permits specified web holes but shows no flange cuts. What is the appropriate field decision?

Show answer & explanation

Correct answer: B - Prevent loading or concealment and obtain a written manufacturer or engineer repair

Domain 10: Roofing/Exterior Walls

Question 8

Construction documents call for asphalt shingles on a 3:12 roof slope. The roofing detail shows only the ordinary single-layer underlayment used on steeper roofs. What revision is needed?

Show answer & explanation

Correct answer: A - Use the low-slope double-coverage underlayment required at 3:12

Domain 11: Associated Trades (including interior and exterior finishes, and windows & doors)

Question 9

A fixed glass pane has 11 square feet of exposed area. Its bottom edge is 16 inches above the floor, its top edge is 68 inches above the floor, and a walking surface is 24 inches horizontally from the glass. The pane is not adjacent to a door. What glazing is required?

Show answer & explanation

Correct answer: C - Safety glazing because all four large-pane triggers are present

Domain 14: Safety OSHA

Question 10

A competent person inspected a 6-foot-deep trench in Type C soil yesterday afternoon. The trench is sloped 1.5 horizontal to 1 vertical, spoil is 2 feet back, and a ladder is within 25 feet of the crew. Heavy rain fell overnight, and no inspection has occurred this morning. Which instruction is required before anyone reenters?

Show answer & explanation

Correct answer: C - Keep employees out until a competent person reinspects the trench after the rain

The rest of the MA-CSL blueprint

The MA-CSL exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more MA-CSL questions with explanations.

Continue in the free practice test →

View plans